Lynchburg, Tennessee
Date: 2021 – 2025
Client: 3 Rivers Energy Partners
The most pressing need for the factory was occasional air-binding in their effluent pipe, robbing them of the ability to discharge from their clarifier. AE2S reviewed the effluent hydraulics and recommended installation of a below grade pump vault to boost the discharge pressure from the clarifier. The vault was constructed in 2022 and there have not been issues with air-binding since it was put into operation. As a result of the wastewater treatment evaluation, several operational improvements have been implemented. Along with the operational improvements, a wastewater chiller system was installed to control the temperature of the wastewater in the biological treatment process. Since the chiller system was installed the wastewater treatment facility has been able to routinely meet its discharge criteria.